Bader Project
All structures at Bader Project are now completed including all auxiliary buildings and process support sundry steelwork
Smaller Projects
The third phase of Twycross Pack house is now completed, and the packing season is soon to start.
We have handed over the structural steel portion for the expansion at the new DHL warehouse at Gosforth Park on 03 March and the sheeting should be completed by 12 March.
The starting of the new Onderberg Packing facility in Malelane was delayed because of the excessive rain we had during January and February this year. If weather permits, we should start as planned with this site on the 8th of March this year.
We are extremely happy to announce that we bought a Peddinghaus beam and saw line and a Peddinghaus automated angle cropper. We are looking to have these two production lines commissioned by the first week of April this year and NJW will be in a position to double our production capabilities. Exciting times ahead.
To learn more about Peddinghaus, view their wonderful video below.
NJW Cold Forming
With the challenging times and the current steel shortages that we are experiencing across the country, we would like to assure our customers that NJW are making all sorts of plans to source coil at different suppliers to meet the high demand.
We are extremely grateful for our commercial quality purlin orders that are increasing every month.
We remind our steel contractor customers that we also manufacture 450MPA Pre-galvanized sag-angle and knee braces for them according to their Tecla drawings.
We will expand on these in our next blog post.